Turn on the electricity of 400KVA Substation at Xuyen A Industrial Park

Turnkey construction of 22KV power line and 400KVA transformer substation, 600m low voltage cables to workshops, Xuyen A Industrial Park, My Hanh Bac Commune, Duc Hoa District, Long An Province.

View the installation dates of the 400KVA transformer: June 18, 2021, May 28, 2021, groundbreaking on May 27, 2021.

Project Name: 22KV power line and 400KVA transformer substation at PV rubber factory.

Location: Plot LB2, Xuyen A Industrial Park, My Hanh Bac Commune, Duc Hoa District, Long An Province

Voltage level: 22KV

Purpose: Rubber production

The construction of a 22KV transmission line and a 400KVA transformer station at Phu Viet rubber plant is being carried out by Quang Anh Electrical Installation Company Limited. Managed by Duc Hoa Power Company in Long An, this is an important project serving the rubber production purpose at Xuyen A Industrial Park, My Hanh Bac commune, Duc Hoa district, Long An province.

Quanganh’s technican install all equipmet before turn on the electricity of 400kva transformer substation at Xuyen A Industrial park

Quanganh’s technican on site work at Xuyen A Industrial park

  1. The first task involved planting 02 14m high LST poles at the 400KVA tower station
  2. installing 2 sets of station cabinet supports
  3. 02 sets of wire stopper supports
  4. 1 insulator support and 01 lightning arrester support.

Quanganh’s technican install 14m concrete pole cabinet on site work at Xuyen A Industrial park

• Construction date: 28/05/2021

Quanganh’s technican on site work at Xuyen A Industrial park

  1. Install 03 FCO and accessories
  2. Install 03 LA and accessories
  3. Install 02 sets of transformer 400KVA supporting brackets
  4. Install 400KVA transformer grounding system
  5. Install LA grounding system
  6. Install 17 sets of porcelain cable supports and accessories for low voltage cable
  7. Install 2 compartments of MCCB 630A & 160Kvar CSPK compensation in 400KVA transformer substation cabinet

Quanganh’s technican install MCCB 630A & 200Kvar compensation cabinet on site work at Xuyen A Industrial park

  1. Pull 511m of 150mm2 low voltage cable from MCCB 630A at transformer substation to factory electrical cabinet
  2. Install 100m of 25mm2 medium voltage cable
  3. Complete 56m of 185mm2 low voltage cable, connect to transformer
  4. Restore construction site to original condition
  5. Install 03 FCO and accessories, Install 03 LA and accessories
  6. Install 02 sets of transformer 400KVA supporting brackets, 400KVA transformer grounding system, LA grounding system
  7. Install 17 sets of porcelain cable supports and accessories for low voltage cable
  8. Install 2 compartments of MCCB 630A & 160Kvar CSPK compensation in 400KVA transformer substation cabinet
  9. Pull 511m of 150mm2 low voltage cable from MCCB 630A at transformer substation to factory electrical cabinet.

Quanganh’s technican install MCCB 630A cabinet on site work at Xuyen A Industrial park

  1. Received the 400KVA transformer from Thibidi factory and crane it to the prepared foundation.
  2. Installed the porcelain support set and installed 03 porcelain insulators.
  3. Connected the CXV 25mm2 medium voltage cable to the high side of the 400KVA transformer.
  4. Connected the CV185mm2 low voltage output cable from the low side of the 400KVA transformer to the 630A main circuit breaker of the transformer station.
  5. Tested the Thibidi 400KVA transformer – Passed the operation standards according to Decision No. 2608/QĐ-EVN SPC.
  6. Tested the 630A Mitsubishi low voltage circuit breaker – Met the operation requirements.
  7. Tested 09 porcelain insulators – Passed the operation standards.
  8. Tested 06 suspension insulators – Passed the operation standards.

Thibidi oil transformer 22/0.4kv 400kva 

  1. Tested 03 Cooper 18KV lightning arrester valves – Passed the operation standards.
  2. Tested 03 Tuấn Ân 200A 27Kv LBFCO polymer insulators – Passed the operation standards.
  3. Tested 03 Tuấn Ân 100A 27Kv FCO polymer insulators – Passed the operation standards.
  4. Tested 03 Tuấn Ân 200A 27Kv LBFCO polymer lightning arrester valves – Met the operation requirements.
  5. Tested the CV 185mm2 0.6/1Kv low voltage output cable – Met the operation requirements.
  6. Tested the grounding resistance – Met the operation requirements.
  7. Tested the CXV 25mm2 24KV medium voltage cable – Passed the operation standards.
  8. Installed the porcelain support set and installed 03 porcelain insulators.

Quanganh install 400KVA transfomer on site work at Xuyen A Industrial park

  1. Cut off 03 LBFCO branch heads
  2. Receive 03 medium voltage transformers from the power company, proceed to remove 03 old transformers from the existing station, and replace them with 03 new transformers.
  3. Complete the connection of the (400+400)KVA substation
  4. Acceptance test the entire substation
  5. At 3pm on 26/06/2021, commission the (400+400)KVA substation and hand over the project to the owner.

Looking for a reliable and experienced contractor to construct a 400kVA substation for your facility? Look no further than Quanganh Construction!

At Quanganh Construction, we understand the importance of having a reliable and efficient power supply for your business operations. That’s why we offer top-notch construction services to design and build high-quality substations for commercial and industrial facilities across Vietnam.

Our team of experienced engineers and technicians has the knowledge and expertise to handle every aspect of the substation construction process, from site inspection and design to installation and commissioning. We use only the highest quality materials and state-of-the-art equipment to ensure that every substation we build meets or exceeds industry standards for safety and reliability.

Quanganh on site work at Xuyen A Industrial park

In addition to substation construction, we also offer a range of other electrical services, including power distribution systems, lighting installations, and transformer substationmaintenance and repair. No matter what your electrical needs may be, we have the skills and experience to get the job done right.

At Quanganh Construction, we are committed to providing our clients with the highest level of customer service and satisfaction. We work closely with our clients to understand their unique needs and requirements, and we always strive to exceed their expectations.

So if you’re looking for a reliable and experienced contractor to construct a 400kVA substation for your facility, look no further than Quanganh Construction. Contact us today to learn more about our services and to schedule a consultation with one of our experts.

 

Video turn on the electricity of 400kva substation site work at Xuyen A Industrial park

QUANG ANH CONSTRUCTION ELECTRICITY CO.,LTD

Website: https://thicongtrambienap.com

Youtube channel: Quanganhcons

Address: 41F/22 Dang Thuy Tram Street, Ward 13, Binh Thanh District, Ho Chi Minh City, Vietnam

Hotline: 0919758191

Email: sales@thicongtrambienap.com

Tax code: 0316365712

 

Exit mobile version