Turn on the electricity of the Bericap 2500KVA substation, Long An

ELECTRICAL WORK FOR NEW 2500KVA TRANSFORMER SUBSTATION AT LONG HAU INDUSTRIAL PARK

Welcome to the new project of Quang Anh Electrical Construction Eletricity at Long Hau Industrial Park, Can Giuoc, Long An! This was a challenging but exciting project that has just completed electrical work and handover to the customer in March 2023. With the cooperation of a dedicated team of experts and employees, we are proud to bring customers quality and reliable electrical construction projects, transformer substations.

This project was designed to meet all the needs of the customer – Bericap Vietnam Co., Ltd., from consulting to design, supply of equipment and materials, and turnkey construction. We are committed to using the most advanced technologies to ensure high performance and durability of the electrical system for the customer’s industrial plant.

Our team is always ready to support customers at any time, ensuring absolute satisfaction of customers. We understand that customers are the most important factor in any project, so we will continuously improve to meet all customer requirements.

The construction of this 22/0.4KV low-voltage and 2500KVA substation electrical system is built to provide power to the industrial factory in Long Hau 3 Industrial Park, Can Giuoc District, Long An Province.

The project is built in Long Hau Industrial Park on plot 3A (Long Hau 3 Industrial Park – phase 1) for the existing and built-to-suit workshop with an area of 11.69 hectares, divided into 5 stages. Phase 1 commenced construction at plot 3A with a total scale of 17,000 square meters, of which about 13,000 square meters are for rent.

Owner: Bericap Vietnam Co., Ltd.

Contractor: Quang Anh Electrical Installation and Construction Company provides materials, equipment and full construction services.

The project is designed with road drilling robots, pulling underground 24KV medium voltage cables 3x70mm2 connected to the 22KV power grid of Can Giuoc Power Company at the 14m centrifugal concrete connection post D2 3P 630A & 03 LBFCO, supplying power to the 2500KVA Kiosk substation using dry-type transformers.

The substation’s medium voltage side is protected by a 630A 24KV Recloser and FDX control panel & 09 LA 18KV cabinet installed on two 14m centrifugal concrete posts. The low-voltage side uses a 3P 4000A 100KA ACB and a 1000Kvar power factor correction cabinet to upgrade the power factor of the substation. The project is expected to be completed and handed over in early March 2023.

The result and effectiveness of the project construction of the electrical system and 2500KVA substation:

With the completion of the electrical substation of 2500KVA by Quang Anh Electrical Installation Company, Bericap factory is expected to have 24 production lines and its long-term goal is to build its own factory with 60 production lines in Vietnam to serve the needs of expanding the market in Vietnam and for export.

Other investors also highly appreciate the potential for development of Long Hau Industrial Park as many large corporations have decided to invest here. Long Hau Industrial Park is becoming one of the large production and business centers in the South, attracting a lot of domestic and foreign investment. With the advantages of geographical location and attractive investment support policies, Long Hau Industrial Park is expected to continue to attract many investors in the future and contribute positively to the economic development of Vietnam

Design, installation, and maintenance consultancy for low and medium voltage electrical systems and transformer stations for domestic and foreign FDI businesses in Long Hau industrial zone

Quang Anh Electrical Construction Co., Ltd is one of the leading companies in the field of constructing low and medium voltage electrical systems and transformer stations in Long Hau industrial zone, Can Giuoc district, Long An province.

With a team of highly skilled engineers and personnel who are rich in experience and have been extensively trained in the electrical field, we are committed to providing our customers with the best services that meet all requirements for constructing low and medium voltage electrical systems and transformer stations.

We offer professional services such as design consultancy, installation, and maintenance of low and medium voltage electrical systems and transformer stations for domestic and foreign FDI businesses in Long Hau industrial zone.

Our products and services meet high technical standards, ensuring safety and efficiency for our customers’ electrical systems.

With the motto “Quality is Trust,” we always prioritize our customers’ interests, committed to bringing them complete satisfaction and absolute trust in our services.

If you have any needs regarding the construction of low and medium voltage electrical systems and transformer stations in Long Hau industrial zone, please do not hesitate to contact us for the best consultation and support. We are ready to meet all of our customers’ requirements.

 

Detail of the project, video and actual construction images.

Project name:

Construction of new 22KV underground medium voltage line and 2500kVA 22/0.4KV transformer substation

Location:

3A-17, Road No. 10, Long Hau 3 Industrial Park (Phase 1), Long Hau Commune, Can Giuoc District, Long An Province, Vietnam

Purpose of the project:

Provide electricity to Bericap Vietnam industrial plant

Mr. Lee Swee Heng – General Director of Bericap Vietnam Co., Ltd – the investor in the ready-built factory at plot 3A said: “After careful research and study, we have decided to invest in Long Hau IP because of its strategic location with good connectivity and developed transportation system to nearby ports, which is convenient for exporting goods. Bericap Vietnam factory invested here has a scale of 6,600 m2 – the 27th plant established worldwide and also our largest project in the Southeast Asia region.”

Testing of the 2500KVA substation before energization:The project is located in plot 3A (Phase 1 of Long Hau 3 Industrial Park) and is planned for both ready-built and built-to-suit factories, covering an area of 11.69 hectares divided into 5 phases. Phase 1 construction began on plot 3A with a total scale of 17,000 square meters, of which approximately 13,000 square meters are floor area for lease. The project is expected to be completed and handed over in early March 2023.

News: Commencement of construction of the new generation ready-built factory in Long Hau 3 Industrial Park

The design of the 2500kva substation:

The robot drilling machine will dig the underground route and pull the 24KV medium voltage cable 3x70mm2 to connect to the 22KV power grid of the Can Giuoc power company. At the centrifugal concrete pole with a height of 14m, D2 3P 630A and 03 LBFCO will be installed to provide power to the 2500KVA Kiosk substation using a dry-type transformer.

On the medium voltage side of the 2500KVA substation, the protection system includes a 630A 24KV Recloser, FDX control cabinet, and 09 LA 18KV installed on 02 centrifugal concrete poles with a height of 14m. On the low voltage side, a 3P 4000A 100KA ACB and a 1000Kvar power factor correction cabinet will be used to improve the power factor of the substation.

2500KVA transformer station

Utilities and services:

Long Hau Corporation (LHC) always focuses on building infrastructure to serve industrial production development. In addition, it also attracts diverse investments from businesses with the same goal of sustainable development, building and investing in utility systems for workers such as accommodation, developing modern and integrated transportation systems, social welfare facilities such as kindergartens, schools, healthcare centers,… to serve workers in the industrial park.

Construction time:

Starting from December 28, 2022 and completing the project on March 28, 2023. The main construction stages are for the 2500KVA transformer substation.

On December 28, 2022:

Commenced construction, planted 02 14m centrifugal concrete poles, and constructed the foundation of a 2500kva kiosk substation.

Planting 02 14m concrete poles

On February 07, 2023:

Installation of medium-voltage equipment at 02 centrifugal concrete poles such as Recloser 24KV 630A, FDX control cabinet, 03 LBFCO, 09 LA, installation of porcelain cross-arms, kiosk shell, MSB cabinet 4000A 100KA, and 1000Kvar compensation cabinet.

The 2500KVA kiosk substation has been delivered to the construction site.

4000A MSB panel &1000Kvar compensation panel

On February 21, 2023:

Installation of a 2500Kva dry-type transformer, excavation of low-voltage underground culverts, and laying of cxv300mm2 low-voltage underground cables.

Installing 2500kva dry type transfomer 

 

Excavating for the HDPE pipe laying.

On February 22, 2023:

Constructing 05 underground high voltage cable heads with 3M70mm2 cross-section, installing and completing low and medium voltage equipment, 4000A 100KA MDB cabinet, and conducting full testing of the 2500KVA transformer station.

4000A MDB Panel

On February 26th, 2023:

Concrete poles of 14m in height were erected to connect the 2500KVA transformer station to the 22KV power grid of the Can Giuoc Power Company. The entire transformer station was cleaned before being energized.

On March 28, 2023:

Quang Anh CE Co., Ltd. in collaboration with the owner company Bericap Vietnam, and the departments of Long An Electricity and Can Giuoc Electricity conducted testing and commissioned the installation of a 2500KVA transformer substation

 

QUANG ANH CE CO.,LTD

Office: 41F/22 Dang Thuy Tram Street, Ward 13, Binh Thanh District, Ho Chi Minh City, Vietnam

Hotline: 0919758191

Email: sales@thicongtrambienap

Website: thicongtrambienap.com –  Youtube channel: Xây Lắp Điện Quang Anh 

Tax code: 0316365712

Construction Images

FDX panel for Recloser 24KV 630A