Jia Bao Rui Plant, Jia Bao Rui Co., Ltd. (VN) is built on lot A-5H-CN, D4 street, Bau Bang Industrial Park, Lai Uyen town, Bau Bang district, Binh Duong province.
Project information: Rooftop solar power project with a capacity of 1.19MWP
Project name: XDM 22KV power line & 1250KVA transformer station at Jia Bao Rui plant
Location: Lot A-5H-CN, D4 street, Bau Bang Industrial Park, Lai Uyen town, Bau Bang district, Binh Duong province
Voltage level: 22KV
Completion date: 11/19/2020
Contractor: Quang Anh Construction Electricity Co.,LTD
Quanganh’s Youtube video on construction work of the 1,19 MWP rooftop solar system & 22KV power line and a 1250KVA transformer station
The rooftop solar power project with a capacity of 1.19MWP at Jia Bao Rui plant was completed on November 19, 2020. The project includes a 22KV power line and a 1250KVA transformer station at Lot A-5H-CN, D4 street, Bau Bang Industrial Park, Lai Uyen town, Bau Bang district, Binh Duong province.
The project is deployed on the roof of Jia Bao Rui plant with a total installation area of about 7,500m2. The rooftop solar power system is integrated with a 22KV power line and a 1250KVA transformer station to supply power to the manufacturing plant.
Built on a large plot of land, the project has brought many benefits to the area, including providing clean electricity and saving electricity costs for the manufacturing plant. At the same time, the project also contributes to reducing CO2 emissions and protecting the environment.
The rooftop solar power project with a capacity of 1.19MWP at Jia Bao Rui plant is a typical example of the application of renewable energy in industrial production in Vietnam. Projects like this help promote sustainable development and ensure energy security for the country.
Xay Lap Dien Quang Anh is a leading contractor in Vietnam in the field of designing, supplying, and installing rooftop solar power systems and large-capacity transformer stations.
![]()
Quanganh’s technician works on the construction site
If you are looking for a reliable partner to implement the construction of large-capacity rooftop solar power projects, install electrical systems, and transformer stations, Xay Lap Dien Quang Anh is the perfect choice for you. With years of experience in this field, Quang Anh is proud to be the leading unit in Vietnam in designing, supplying, and constructing rooftop solar power systems and transformer stations.
The rooftop solar power project with a capacity of 1.19MWP at Jia Bao Rui plant is one of Quang Anh’s most successful projects. With a professional staff and a modern system of equipment and machinery, Quang Anh is committed to providing high-quality services and meeting all customer requirements.
If you need to install a rooftop solar power system in Bau Bang Industrial Zone, industrial zones in Binh Duong area, and neighboring provinces, please contact Xay Lap Dien Quang Anh for the best consultation and support. We commit to providing customers with cost-saving solutions, environmental protection, and the most efficient use of renewable energy.
Contact Xay Lap Dien Quang Anh now at Hotline: 0919758191 for the best consultation and support for your project!
QUANG ANH CE CO.,LTD
Office:Unit 02, 08th floor, Pearl Plaza Building, 561A Dien Bien Phu Street, Ward 25, Binh Thanh District, Ho Chi Minh City, Vietnam
Hotline: 0919758191
Email: sales@thicongtrambienap
Website: thicongtrambienap.com – Youtube channel: Quanganhcons
Tax code: 0316365712
Main scope of word on construction site
Installation of 12m BTLT pole without guy wire, in accordance with the regulations of PC Binh Duong.
Installation of grounding well at the transformer station and metering pole.
Thibidi 1250KVA transformer
![]()
The project uses a 1250KVA oil-immersed transformer 22/0.4Kv manufactured by Vietnam Branch.
![]()
Recloser 24KV-630A-12.5KA/3S self-closing switch
The Recloser 24KV-630A-12.5KA/3S self-closing switch, control cabinet, voltage transformer for measurement, protection and power supply voltage transformer are all installed at the same location on the non-guyed BTLT pole.
ACB 2000A electrical cabinet
MSB electrical cabinet includes 1 ACB 2000A 65kA module, 1 500 KVAr automatic compensation module using Mitsubishi circuit breakers, and Samwha capacitors.
Medium voltage measurement
TU and TI medium voltage metering system is installed on the non-guyed BTLT pole right at the 1250KVA transformer station.
Commissioning of 1250KVA transformer substation
The 1250KVA transformer substation project was fully designed, constructed, and commissioned by Quang Anh Electrical Installation Co., Ltd. and put into operation on November 19, 2020.
Tính nhanh giá trạm biến áp
Chọn công suất và chiều dài tuyến để xem giá tham khảo cùng thông số điện.
Gửi yêu cầu báo giá theo thiết kế
Gửi thông tin công trình, BOQ hoặc bản vẽ để nhận báo giá chính thức. Các trường có * là bắt buộc.
Phạm vi báo giá
Áp dụng cho một trạm mua điện EVN, máy dầu 22/0,4 kV (máy một pha: 12,7/0,23 kV), TU/TI trung thế do EVN cấp. Giá gồm thiết bị theo cấu hình, lắp đặt, tiếp địa, liên kết máy–CB tổng, hồ sơ thiết kế–đấu nối và phối hợp thí nghiệm, nghiệm thu điện lực.
Kios, trụ thép hợp bộ và trạm trong nhà có tủ trung thế cùng đoạn cáp ngầm theo thông tin đã nhập. Các kiểu ngoài trời dùng phương án bảo vệ tương ứng; sơ đồ cuối cùng cần phù hợp yêu cầu đấu nối tại công trình.
Chưa gồm VAT, cáp từ tủ trạm đến MSB/phụ tải, hotline, cuộn kháng lọc hài, nền yếu/cọc đặc biệt, đất và PCCC đặc thù. Tuyến ngầm tính theo điều kiện thi công thông thường, chưa gồm khoan qua đường hoặc hoàn trả đặc biệt.
Giá dùng để tham khảo đầu tư. Báo giá chính thức được xác nhận sau khảo sát và thống nhất cấu hình. Thông số điện là lựa chọn sơ bộ, cần kiểm tra theo thiết kế trước khi thi công.
Dải công suất và điều kiện áp dụng
Danh mục là phạm vi tiếp nhận yêu cầu của công cụ, không phải giới hạn công suất chung của TCVN. Trạm treo một máy: 15–100 kVA; bộ ba máy: 3×15–3×100 kVA. Giàn: 100–630 kVA. Trụ thép: 100–630 kVA; 750/800 kVA cần xác nhận thiết kế và chấp thuận tại địa phương. Nền/kios/phòng: danh mục 50–10.000 kVA, không có nghĩa mọi cấu hình đều có giá trọn gói hoặc cùng kết cấu.
Tham khảo QĐ 1299/QĐ-EVN ngày 03/11/2017, Tập 1, mục 3.3–3.4; kiểm tra văn bản hiện hành của điện lực quản lý trước khi triển khai. Kios phải phù hợp định mức/thử nghiệm của nhà chế tạo (IEC 62271-202); phòng/nền phải đáp ứng bố trí, thông gió, kết cấu và PCCC của dự án. Công suất trạm nhiều máy phải tách số máy và công suất mỗi máy.
Công cụ do QuangAnhcons phát triển · © 2026 QuangAnhcons. Mã nguồn theo GPL-2.0-or-later; tiêu chuẩn và dữ liệu hãng thuộc chủ sở hữu tương ứng.